Khan Altai Resources LLC is dedicated ...

Discovery Khan Altai Gold Deposit.
The JORC technical review of the exploration conducted by SRK Consulting was completed, metallurgical test work was finalized at ALS Metallurgy Australia, the resource calculation was registered with MRPAM, the JORC resource estimate of 41.5 tonnes of gold (1.33 million ounces) by SRK Consulting was confirmed, and the mining license MV-021537 was subsequently acquired.


Haul track construction commenced, the oxide ore resource was registered with MRPAM, and a total of 38,000 meters of drilling was completed.
The JORC reserve report was updated, 40,000 meters of drilling was achieved, an Environmental Impact Assessment was initiated, and construction commenced for the ADR plant, camp, and related infrastructure sub-projects.


State commissioning of the ADR plant was completed, ore crushing and heap leaching operations commenced, reagent storage was commissioned, and flotation tests on the primary ore were conducted.
Gold production commenced, construction of the camp, SOS office, laboratory, and HME truck shop continued, development of heap leaching pad cells 7 to 9 advanced, and a comprehensive 50,000-meter drilling program was undertaken to expand the resource base.


A stationary crusher with a capacity of 4 million tons was installed, the flotation plant project was implemented, mining capacity and the crushing fleet were enhanced, and preparations and permitting for the construction of a primary ore processing plant were carried out.